81. | Review Contractors' HSSE procedures/ plans, such as heavy lifting operations and for high and complex structures. |
| 审核承包商的HSSE作业程序/划,如:大型吊装和超高、状复杂物体或主体结构吊装。 |
|
|
| |
82. | crawler crane |
| 履带式起重机 |
|
|
| |
83. | Lo-Lo carbulk carrier |
| 集装箱吊装、汽车和散货多用运输船 |
|
|
| |
84. | tracked diesel crane |
| 履带式柴油起重机 |
|
|
| |
85. | Assembly equipment and assembly method differs as span, weight and installation height of girder. |
| 钢梁的跨度、量和安装高度不同,适合的吊装机械和吊装方法亦随之而异。 |
|
|
| |
86. | Colligation point of girder should ensure stability of assembly, otherwise, temporary fixation should be carried out before assembly. |
| 钢梁的绑扎点要保证钢梁的吊装稳定性,否则就需在吊装前进行临时加固。 |
|
|
| |
87. | crane ,jib (excl. portal and pedestal cranes), not self-propelled |
| 非自动悬臂起重机(门式臂起重机及支座式悬臂起重机除外) |
|
|
| |
88. | travelling bucket crane |
| 移动式抓斗起重机 |
|
|
| |
89. | crane ,jib (excl. portal and pedestal cranes), self-propelled |
| 自动悬臂起重机(门式臂架起重机及支座式悬臂起重机除外) |
|
|
| |
90. | wheel-mounted crane |
| 装车轮起重机 |
|
|
| |